S&P upgrades Skeena Resources outlook on mine progress
S&P Global Ratings revised its outlook on Skeena Resources Ltd. to positive from stable on Wednesday while affirming its ’CCC+’ issuer-credit rating on the company. The rating agency cited progress on the company’s Eskay Creek project in British Columbia, which Skeena reports is more than 70% complete as of Aug. 31, 2026.
The project has advanced from about half complete when S&P Global Ratings assigned its rating in March 2026. Recent work includes crusher installation and conveyor work, along with installation of key processing plant equipment such as grinding cyclone clusters, the concentrate thickener, flotation cells, and SAG and ball mills. Skeena reports it has completed about 92% of detailed engineering work.
S&P Global Ratings assumes Eskay Creek will begin producing in late 2027 and could generate more than C$600 million of annual free operating cash flow once it achieves steady state production. The rating agency bases this on assumptions that the project will benefit from high-grade deposits, low unit costs, and a long-term gold price of about US$3,300 per ounce.
The ’CCC+’ rating continues to reflect S&P Global Ratings’ view that Skeena lacks an operating track record and faces risks that make it dependent upon favorable business, financial, and economic conditions to meet its financial commitments. The project involves reopening a mine in the Golden Triangle region of British Columbia that Barrick Gold Corp. operated as an underground mine between 1994 and 2008.
S&P Global Ratings said it could raise the rating within the next 12 months if Skeena nears completion of Eskay Creek while maintaining sufficient liquidity. The rating agency could revise its outlook to stable if it expects significant development cost overruns or delays that could exhaust the company’s liquidity.