Midtown NYC building ‘shifting’ and in danger of ‘localized collapse’: officials

Midtown NYC building ‘shifting’ and in danger of ‘localized collapse’: officials

A Midtown high-rise whose support columns were discovered buckling Tuesday was “shifting’’ and in danger of partially collapsing — a situation so precarious that crews couldn’t even go in to stabilize it, authorities said.

The 37-story former Pfizer headquarters on East 42nd Street —  which is being converted from commercial to residential use — was dramatically evacuated during the morning rush along with eight surrounding buildings as nine blocks were closed down and city officials mounted a desperate effort to avert catastrophe.

“The concern is that since we have been on site in the early morning, we have seen continued shifting of the structure,” Mayor Zohran Mamdani said early Tuesday afternoon.

Buckling support columns on the 21st floor of a 37-story building.
A bent support beam inside of the Midtown building. Obtained by NY Post
FDNY vehicles respond to a possible building collapse on 42nd Street in New York City.
The entire building on 42nd St. was evacuated after it started buckling on Tuesday morning. William Farrington for NY Post

FDNY crews and other emergency responders have been monitoring the building with sensitive equipment and chillingly discovered the still-unfolding precarious situationhigh above the crowded streets of Manhattan, the mayor said.


Follow live updates on Mayor Zohran Mamdani’s socialist agenda and the latest in NYC politics


“The way this building is constructed, it’s a steel-frame building, so it would not be a total collapse, it would be more of a localized collapse,” said FDNY Chief of Department John Esposito.

“That remains our concern – that it’s moving. … We have seen continual movement. It does mean it is not stable.”

When asked if that means the building could collapse into itself like a pancake, Esposito responded, “Possibly.”

Exterior view of the 21st floor of 235 East 42nd Street showing structural issues with buckled columns, cracks, and sagging floors during its conversion into a residential building.
This week’s inclement weather could worsen the situation, officials say. @FDNY
New York City Mayor Zohran Mamdani speaks at a podium with a
Mayor Zohran Mamdani and city officials giving an update on the evacuated building at a press conference. AP Photo/Angelina Katsanis

A source at the scene with direction knowledge of the situation said, “It’s like squeezing both ends of a twig.

“And it is buckling,” the source said, explaining the breach occurred at the connection point between the building’s old and new sections.


Here’s the latest on the evacuated Midtown building in danger of a ‘localized collapse’:

  • Crews work to prop up Midtown NYC high-rise that suddenly buckled — as cause remains a mystery
  • NYC Pfizer building developer tries to downplay collapse risk — insists high-rise buckling is a ‘freak accident’
  • Buckling building in Midtown NYC will face partial demolition — but even stabilizing it beforehand will be highly risky: experts
  • NYC buildings commissioner confident buckling Midtown building is ‘stabilizing’ after emergency work
  • Massive ‘frozen zone’ around buckling Midtown NYC building leaves hundreds out on street — with no idea when they can return

There is concern that rain and wind expected later in the week could only worsen the situation, sources said.

Six officials — including from the FDNY, city Buildings Department and the contractor — entered the structure midafternoon to begin trying to better assess the damage and how to stabilize it, sources said — noting it did not appear to have shifted for about two hours.

New York City Buildings Commissioner Ahmed Tigani (center, vest and hardhat) surveying a collapsed building with FDNY personnel.
New York City Buildings Commissioner Ahmed Tigani (center in vest) arriving at the scene of the evacuation. X/Dept of Buildings

Authorities were flying drones around the site, seeming to focus on the back of the building.

The news conference also revealed other heart-pounding new details about the harrowing engineering problem.

Mayor Zohran Mamdani said the Department of Buildings was investigating the scene of a structurally unstable building in Midtown using FDNY drones.

A viewer spotted this drone flying in the vicinity of the building Tuesday afternoon.

📸: @themarccuddypic.twitter.com/Mt5PkFS5eN

— Spectrum News NY1 (@NY1) July 7, 2026

NYPD and FDNY officials instituted a “frozen zone from East 40th to 45th streets between First and Third avenues, barring all pedestrian and vehicle traffic for fear the building could shower debris below.

Mamdani said two structural columns have buckled inside the building’s 21st floor, while another one shows movement.

“The building remains unstable,” he said.

Buckled support column on the 21st floor of the former Pfizer building at 235 E. 42nd St.
The former Pfizer headquarters is “shifting” and in danger of partially collapsing, according to officials. Obtained by NY Post
Damaged support columns and exposed construction inside a building.
Work crews are unable to even enter the building to stabilize it due to safety concerns. New York Post

The building at 235 E. 42nd St. near Second Avenue and is considered one of the largest commercial-to-residential conversion projects nationwide, with 1,600 apartments slated by 2027.

Contractors had been adding 11 new floors on top of a 22-story section of the building, said city Buildings Commissioner Ahmed Tigani.

Sources said the compromised sections appear to be the 17th and 21st floors, below the additions.

Emergency personnel, including firefighters and police, gather on a city street after a high-rise evacuation due to structural failure.
FDNY and other officials outside of the evacuated building on 42nd St. James Keivom for NY Post
Spectators gathered behind yellow tape to view a midtown high-rise building evacuated due to structural failure.
Spectators gathered on 42nd St. after the high-rise was evacuated. James Keivom for NY Post

Tigani said cause will be investigated, but it’ll first have to be made safe.

He said emergency beams and columns likely would need to be brought in to shore up the floor.

Investigators likely will look into several potential causes, including whether the original design or construction was deficient, said a structural engineer. speaking to The Post on behalf of the Structural Engineers Association of New York.

“Could be one or all of many things, which will be investigated once the building is shored,” the engineer said. “Possible overload of floors with construction materials, possible removal of a structural element during a prior renovation that wasn’t known, original deficiency in design or construction.”

One source said investigators could also look into whether the steel was changed from the original plans during construction.

“This is a minute-by-minute assessment,” Mamdani said, as he warned New Yorkers to stay away.

-Additional reporting by Georgett Roberts