A single hyperscale AI campus can cost more than $20 billion to build, and its value could double once GPUs and other equipment are installed. However, insurers and reinsurers cannot provide the full coverage limits developers and lenders need at competitive rates through traditional construction policies.

AI data centers rely on interconnected power systems, advanced cooling, backup batteries, and expensive computing equipment. A failure in one area can cause major property damage and business interruption.

Swiss Re projects that global data center insurance premiums will rise from $10.6 billion to $24.2 billion by 2030. Yet growing demand does not guarantee sufficient coverage. This gap could complicate project financing, raise infrastructure costs, and increase risks for lenders and investors, while creating opportunities for insurers to cover these complex assets.

Why AI Data Centers Are Becoming Harder to Insure

Traditional infrastructure projects, such as bridges and tunnels, usually require $5 to $10 billion in insurance coverage, while large AI data center campuses may need two to three times that amount.

However, individual insurers cannot cover such large projects alone. For example, Munich Re offers up to $250 million in coverage per data center. This means that a $10 billion project could require more than 40 insurers to provide enough coverage. 

Aon has also introduced a dedicated insurance program for data centers that offers up to $5 billion in coverage, an increase from $3.5 billion in April.

The location of these facilities adds to the challenge. Swiss Re estimates that more than a quarter of US data center capacity is in areas that experience at least three days of large hail each year. More than 40% is in areas with significant tornado risk. 

Zurich also reports that 64% of data center capacity under construction in 2026 is outside established locations such as Northern Virginia.

The main concern is not that data centers are likely to suffer losses every year. Instead, the risk comes from having billions of dollars of equipment and infrastructure concentrated in one location. A single disaster could damage the facility, interrupt operations, and trigger cyber-related insurance claims at the same time.

Insurers See an Opportunity, but Lenders Want More Protection

Insurers see data centers as a growing business opportunity. Swiss Re Institute forecasts that data center insurance premiums will total $91 billion between 2026 and 2030, with property insurance accounting for $49 billion. S&P also expects data center construction insurance to generate about $10 billion in premiums in 2026.

However, insurers are reluctant to cover the full replacement cost of every data center. Rather, they are exploring ways to spread the risk by dividing coverage among several insurers, adjusting policies as different construction phases are completed, and setting coverage limits based on the estimated size of a potential loss.

This could make it harder for developers to secure financing for large AI data center projects. Lenders generally want insurance that covers the full value of a project, while insurers prefer limits that reflect the losses they are willing to take on. 

How Insurance Gaps Could Affect Data Center Financing

Hyperscalers can accept partial insurance coverage because they have the resources to absorb some losses. Some use captive insurers to cover risks that external insurers will not take.

Investment funds and private lenders have less flexibility. Many lack the technical experts needed to assess whether a data center can withstand major failures. As a result, they may reject projects that lack full insurance coverage, even when those projects are financially viable.

For instance, KKR and Blackstone have turned down some data center loans because natural disaster insurance was insufficient.

Refinancing could make the problem worse. As tens of billions of dollars in data center construction loans mature, replacing this financing will require pension funds and insurers, which typically want coverage for the full value of the assets.

Insurers also face the risk of being exposed to the same data center in multiple ways. Bank for International Settlements warned that insurers are increasingly exposed to debt used to finance AI infrastructure. 

An insurer could cover a data center and also invest in loans tied to it. If the facility suffers a major loss, both investments could be affected.

Who Benefits and Who Faces the Risks?

The insurance shortage benefits some cloud providers. Hyperscalers are on track to spend up to $900 billion on capital expenditures and AI infrastructure in 2026. Their strong finances and in-house insurance companies allow them to absorb risks that smaller competitors must pay insurers to cover.

The pressure falls on data center developers and cloud providers that borrow heavily to build their facilities. Limited insurance coverage could make loans more expensive, lead to stricter lending conditions, or reduce the number of investors willing to refinance debt.

Insurance brokers could benefit from the growing demand for coverage. Companies such as Aon and Marsh help developers combine policies from multiple insurers to reach the required coverage limits. This makes their expertise more valuable.

Reinsurers such as Swiss Re and Munich Re could also earn more from rising premiums. However, S&P advises insurers to carefully manage their exposure to risks concentrated in the same locations. A major disaster could trigger large claims across several policies.

Investors can see whether lenders accept insurance based on estimated potential losses rather than full asset value, whether data center risks enter insurance-linked securities, and whether developers disclose how much of their facilities’ replacement value is insured. 

These indicators will show whether the insurance market is adapting to the growing cost of AI infrastructure.

Bottom Line

AI data center expansion is creating an insurance shortage that could become a financing problem for the industry. While major cloud providers can absorb some risks, smaller developers may face higher borrowing costs and difficulty securing loans. 

Insurers and brokers stand to benefit from rising demand, but their ability to provide enough coverage will determine how easily new projects get funded. 

For investors, the key question is whether insurance capacity can keep pace with the growing cost and concentration of AI infrastructure.