An earthquake with a magnitude of 7.1 and maximum intensity of 7 on the Japanese scale struck Kumamoto Prefecture on Tuesday. Highway damage has been reported as of 6:00 p.m. local time, with closure measures being implemented.

Kumamoto Prefecture experienced a similar-scale earthquake in 2016, which affected production activities in the semiconductor and automotive industries.

Citi noted that the current impact appears less severe than the 2016 event. In 2016, earthquakes with maximum intensity 7 occurred on April 14 and April 16.

Company disclosures from the 2016 earthquake showed that partial production resumptions required approximately 2-4 weeks. Recovery to normal operations required 1-4 months, depending on the extent of the damage.

Renesas Kawashiri Plant and Fujifilm Kyushu restored production capacity in roughly a month during the 2016 earthquake. Mitsubishi Electric’s Kumamoto Plant, Mitsui High-tec, Horiba Stec, and Tokyo Electron Kyushu recovered in approximately 1-2 months. Sony Kumamoto TEC took until the end of July to fully recover.