Lanarkshire AI datacentre to fully rely on National Grid despite renewables claim
DataVita has revised plan for Chapelhall development to be wholly powered by 1GW of renewable energy A datacentre company that said it would power a massive AI development near Glasgow with renewable energy has admitted that the scheme will be entirely served by the National Grid. DataVita, a key plank of the UK’s AI strategy, had promised that the Lanarkshire project would draw 1GW – the...
A datacentre company that said it would power a massive AI development near Glasgow with renewable energy has admitted that the scheme will be entirely served by the National Grid.
DataVita, a key plank of the UK’s AI strategy, had promised that the Lanarkshire project would draw 1GW – the equivalent output of a small nuclear reactor, or Britain’s largest windfarm – from green sources. But when the Guardian raised questions about the pledge, it said the arrangement was “subject to final commercial agreements, planning, grid and consenting processes”.
Now, the company, which says its proposals would transform the economy of the village of Chapelhall, outside Airdrie, has quietly revised the plan. It now says the datacentres will be “fully grid served” with the possibility that solar and windfarms “could connect in the future”.
DataVita says the power it draws from the grid will be largely renewable energy. The company remains in receipt of £202m of public money in the form of wealth guarantees from Britain’s national wealth fund.

While the shift may appear to have been inevitable given the implausibility of the claimed renewables provision, it could present a problem for both DataVita and Britain’s AI strategy.
Under the former prime minister Keir Starmer, Britain’s AI strategy was to build massive datacentres in zones across the country. Their developers would get incentives – including, potentially, discounts on energy and expedited planning approvals. DataVita was to build one of the key developments associated with this strategy, an “AI growth zone” in Lanarkshire.
But this strategy began to founder just over a year after it was announced, when the Guardian’s investigations demonstrated that there was little solidity behind many announced plans.
AI datacentres are some of the most energy-intensive structures humanity has ever built, and energy costs are higher in Britain than in most of Europe. There is a years-long wait for the UK developments to connect to the grid.
Two key UK AI investments – announced with great fanfare by Starmer’s government – are on shaky ground after questions emerged over their ability to power themselves, or pay the high energy costs necessary to realise their stated ambitions. Now DataVita, which was supposed to bring 3,400 jobs to Lanarkshire by building a 500MW datacentre, also appears to be backtracking on its energy plans.

In a response to the Guardian, the company said it had not misrepresented its intention to supply renewables to the site earlier this year. “Our commitment to renewable energy is unchanged,” said a spokesperson. However, they added: “Our datacentres are being designed to be grid served … Our grid supply will be through a renewable power purchase agreement.”
This appears to contradict an earlier announcement, in which the company said: “More than 1GW of renewable energy capacity, including wind, solar, and battery storage, will be delivered through private wire connections directly linked to the datacentres.”
DataVita left open the possibility that its datacentres would connect to renewable energy in the future, through a wind and solar park it proposes to build in North Lanarkshire.
Kat Jones, the director of the Edinburgh-based charity Action to Protect Rural Scotland, said DataVita’s apparent change in direction was “emblematic of the hyperbolic claims being made by datacentre developers in Scotland”.
“Hyperscale AI datacentres simply cannot run on renewable power alone, they absolutely need a highly reliable source of grid power,” she said. “It is not surprising that the goalposts have now changed.”
Related Articles
- Business News
The datacentre next door: on the frontline of tech’s latest David v Goliath battle
- Business News
UK government met 137 businesses over AI datacentres – but no environmental groups
- Business News
Government urged to ‘back Scotland’s pipeline in strategic energy plans’
- Business News
The datacentre arms race hits pause in south-east Asia
- Stock Markets News
Explainer-Why AI data centers are powering a boom in fuel-cell demand