TeraWulf Inc. (NASDAQ:WULF) shares rose 4.7% in premarket trading Tuesday following the company’s announcement of acquiring a hyperscale high-performance computing development site in Eastern Kentucky.
The acquisition establishes the Muskie Data Campus, which is expected to support more than 1 gigawatt of data center capacity over time. TeraWulf acquired the site from Industrial Equity Partners.
Delivery of the initial 500 megawatts is expected to ramp beginning in the second half of 2028, with an additional 500 MW targeted for delivery in the second half of 2030. The campus is located within the 1,000-acre EastPark Industrial Park and includes approximately 285 acres of owned and controlled land.
Kentucky Power, an AEP Company, is constructing a 345 kV substation connected to the existing 765 kV transmission network, providing redundant, utility-scale power infrastructure designed to support the full 1+ GW campus. Transmission infrastructure and energy service agreements were executed concurrently with the acquisition.
"This acquisition further reinforces the strategy we discussed on our first quarter earnings call: securing and developing large-scale, power-advantaged sites capable of supporting the next generation of HPC workloads," said Paul Prager, Chairman and Chief Executive Officer of TeraWulf.
The site is already zoned for its intended use, with permitting activities underway and limited site work required to support data center construction. The Muskie Data Campus represents TeraWulf’s second major digital infrastructure campus in Kentucky, alongside the company’s 480 MW Justified Data campus in Hancock County.
Regional economic development leaders have identified the project as one of the most significant economic development opportunities in northeastern Kentucky in decades.