Fermi America stock rockets on $6.5B TensorWave lease deal
Fermi America LLC (NASDAQ:FRMI) shares jumped 35% in after-hours trading Monday following the announcement of a 15-year, $6.5 billion lease agreement with TensorWave for its Texas AI campus.
The lease between Fermi’s subsidiary Fermi Campus 1 LLC and TensorWave TEX1, LLC covers a facility supported by 222 megawatts of total facility power at the Project Matador campus in Carson County, Texas. The first phase is set to deliver a complete turnkey data center solution beginning in the second half of 2027.
The agreement includes expansion rights for two additional data centers that would bring the total partnership to more than 650 MW across three phases. Once fully delivered, the facility is expected to support tens of thousands of next-generation AMD Instinct GPUs for large-scale AI training and inference.
Fermi said it expects certain obligations under the lease to be guaranteed by one of the global leaders in AI. The lease contains customary conditions, including the receipt of requisite project guaranties and financing.
Construction at Project Matador is underway, with approximately 6 gigawatts of the planned 17 GW already permitted and more than $1.5 billion invested in the buildout to date. The company is targeting first power for 2026.
The initial 15-year term includes two renewal options of five years each. Fermi said it continues to advance discussions with additional hyperscale, neo-cloud and enterprise compute counterparties for capacity at Project Matador.
The Texas Tech University System, which has partnered with Fermi on the project, said it supports the transaction and intends to work closely with Fermi toward a successful closing.