XTX Markets Opens Finnish Data Center, Says Red Tape Puts Expansion at Risk
XTX Markets has opened its first own data center, a 22.5-megawatt facility in Kajaani, Finland, the London-based trading firm said today (Tuesday). It warned that slow permits for new power lines could put further investment there at risk. Power is...
XTX Markets has opened its first own data center, a 22.5-megawatt facility in Kajaani, Finland, the London-based trading firm said today (Tuesday). It warned that slow permits for new power lines could put further investment there at risk.
Power is secured for two buildings. XTX said electricity and grid connections cover only the first two facilities on the 193-hectare campus, while a third, already under construction and due in mid-2028, has no guaranteed supply yet.
That leaves the site well short of the 250 megawatts XTX aimed for when the Kajaani plan surfaced in April 2024. The capacity now running equals 9% of that target, by FinanceMagnates.com's calculation.
XTX said it has spent more than €400 million (about $465 million) on construction so far, mostly with Finnish contractors. That is roughly 40% of the more than €1 billion it earmarked for the site in January 2025.
Power Line Permits Now Take Years
The delay XTX describes concerns the lines that would carry electricity to the later buildings. Mike Irwin, chief operating officer at XTX Markets, singled out permits to expropriate land for those lines.

"Expropriation permits that once took months can now take years," Irwin said.
He said government bureaucracy and a lack of engagement were putting plans to invest billions more at risk. XTX would contribute financially to infrastructure, he added, but without that engagement future investment decisions would be called into question.
Finnish public broadcaster Yle reported that XTX plans five data centers along the Kajaani River and would build faster with enough power. Three of the five therefore depend on electricity that is not yet secured.
From a Leased Site to Its Own Campus
Kajaani was built to end XTX's reliance on rented computing. When the €1 billion figure came out, then-Chief Technology Officer Joshua Leahy said the firm's need for compute had outgrown leasing options. Leahy left XTX and its board in March 2026.
The move off leased space is now done for storage. In one six-week window, XTX said, it shifted 417 petabytes on 385 servers, roughly 17,000 drives weighing 26 metric tons, from a rented data center five kilometers away. The second building is due to start operating in 2027.
A Profitable Firm Asking for Grid Access
Money is not the constraint XTX names. Its three UK entities reported combined net revenue of £3.93 billion (about $5.3 billion) for 2025, up 43% from a year earlier, and profit after tax of £1.71 billion.
The firm, controlled by founder Alex Gerko, ran more than 25,000 graphics processing units for research in 2024, mostly from Nvidia. Its models price more than 53,000 instruments.
The Kajaani site employs more than 30 full-time staff and has room for 50. XTX also pledged more than €1.6 million to Finnish education projects, including €520,000 for Kajaani University of Applied Sciences.